One-piece Molding Sandal PU Production Line Full Solution

This professional production line adopts advanced one-piece (upper & sole) molding technology for sandals and beach shoes. It realizes glue-free integral forming, featuring high bonding strength, stable product quality and high continuous production efficiency. All equipment is matched according to mass production standards, suitable for medium and large-scale footwear factories.
Technical Document | June 2026 Haifeng Machinery
One-piece molding sandal
Beach shoe finished product

Industry Pain Points & Common Defects

01
Poor Upper-Sole Adhesion and Delamination in Wet Environments
Traditional gluing limitations:
Traditional glued sandals and beach shoes easily suffer from degumming and sole detachment when exposed to water, sand, and sunlight.
Insufficient surface roughening:
In one-piece molding, if the bonding surface of the shoe upper is insufficiently roughened or if release agent is sprayed unevenly onto the upper, PU adhesion strength will drop significantly.
Targeted solution:
Strengthen upper surface treatment with a dedicated Roughening Machine (1200mm working width) and standardize release agent application via a 7KG load Spraying Robot.

02
Internal Bubbles and Material Overflow During PU Injection
Internal bubbles:
Caused by unqualified vacuum tightness or moisture in the two-component PU raw materials (Polyol A & Isocyanate B). Sealing the material tank and preheating raw materials in a 2.5m³ drying oven (60–70°C) eliminates moisture-induced foaming defects.
Material overflow:
Caused by mold misalignment, inaccurate shoe upper lasting, or excessive injection volume.
Targeted solution:
Use a Shoe Upper Lasting Machine for accurate positioning, adjust mold closing precision, and calibrate the Special PU Casting Machine within ±0.5% metering accuracy.

03
Incomplete Curing and Continuous Mass Production Bottlenecks
Incomplete curing:
Low oven temperature or insufficient curing time leads to soft soles, deformation upon demolding, and unstable physical properties.
Cycle & efficiency balance:
Achieving a stable 6–7 minutes single cycle time per pair (2,050–2,400 pairs per 8-hour shift) requires synchronizedheating parameters and conveyor line speed.
Targeted solution:
Integrate a constant-temperature Curing Tunnel with an Automatic Conveyor Line (45–55KW) and Servo Mold Opening & Closing Units for seamless continuous production.

Core Process Features
Custom Mold and Shoe Last

The one-piece molding process integrates shoe last, upper and sole into one set of molds. PU material is injected and cured in one step to tightly combine the sole and upper. No adhesive is needed, and the finished product has excellent structural strength, wear resistance and durability, which greatly simplifies the traditional gluing process.

Basic Project Parameters
Item Specification
Raw Material & Ratio Two-component PU: Polyol (A) : Isocyanate (B) = 100 : 40 ~ 70
Preheating temperature: 60 ~ 70℃
Auxiliary Materials Release agent, pigment, MC (mixing head cleaning), DOP (tank cleaning)
Casting Performance Max flow: 70 g/s | Metering accuracy: ±0.5%
Control System HMI manual/semi-automatic, multi-formula storage
Applicable Product Beach shoes & sandals (one-piece upper & sole molding)

Complete Production Process

Production process flow chart
One-piece sandal production process flow
Procedure Detailed Description Equipment Picture
Shoe Upper Cutting Cut raw materials into standard upper shape Hydraulic Cutting Machine
CNC Pneumatic Cutting Machine
Cutting machine
Surface Roughening Process bonding surface to improve PU adhesion Roughening Machine Roughening machine
Lasting Fix upper on shoe last for accurate positioning Shoe Upper Lasting Machine Lasting machine
Mold Preparation Clean mold, spray release agent, place last & upper Release Agent Spraying Robot
Custom Mold & Shoe Last
Spraying robot
PU Injection Molding Mix A/B materials and inject into mold Special PU Casting Machine Casting machine
Mold Curing Constant temperature curing in tunnel Curing Tunnel Curing tunnel
Demolding & Finishing Take out products, trim edges, inspect & package Mold Opening & Closing Unit
Edge Trimmer
Trimming & Sorting Line
Mold opening unit


Demolding, Trimming & Quality Inspection Process
Mold opening process
Mold Opening & Demolding
Servo-driven mold opening & closing units ensure smooth demolding of one-piece molded sandals without damaging the sole or upper.
Edge trimming
Edge Trimming
Dedicated edge trimmers cleanly remove flash and burrs along the parting line for a smooth, refined shoe contour.
Quality inspection
Inspection & Packaging
Comprehensive appearance and bonding inspection on the trimming & sorting line before final packaging.

Full Equipment List

1. Cutting & Preparation Equipment
Equipment Name Quantity Key Specifications Picture
Hydraulic Cutting Machine 1 set Cutting force 25~100T, power 3~7.5KW Hydraulic cutting machine
CNC Pneumatic Cutting Machine 1 set Feeding accuracy ±0.1mm, power 2.2~7.5KW CNC cutting machine
Roughening Machine 1 set Working width 1200mm, power ≈2.3KW Roughening machine

2. Molding & Curing Equipment
Equipment Name Quantity Key Specifications Picture
Special PU Casting Machine 1 set Max flow 70g/s, accuracy ±0.5%, power 20.55KW PU casting machine
Curing Tunnel 1 set Size 2000×1150×1000mm, power 0.55KW Curing tunnel
Mold Opening & Closing Unit 2 sets Servo motor, power 2KW Mold opening unit
Custom Mold & Shoe Last Several Customized by shoe size Custom mold

3. Auxiliary Equipment
Equipment Name Quantity Key Specifications Picture
Raw Material Drying Oven 1 set Volume 2.5m³, max temp 90℃, power 6.55KW Drying oven
Air Compressor & Tank 1 set Power 22KW, exhaust 3.2m³/min Air compressor
Industrial Chiller 1 set Cooling capacity 6.02KW, power 1.91KW Industrial chiller
Automatic Conveyor Line 1 set Total power 45~55KW Conveyor line
Cleaning & Release Agent Tank 2 sets Size 300×300×1000mm Storage tank
Release Agent Spraying Robot 1 set Load 7KG, power 1KW Spraying robot
Raw Material Mixer 1 set Uniform mixing of A/B components Raw material mixer
Trimming & Sorting Line 1 set Edge trimming, inspection and packaging Sorting line
Edge Trimmer 1 set Finish trimming for finished shoes Edge trimmer

Production Capacity & Efficiency
Index Data Remark
Single Cycle Time 6 ~ 7 minutes per pair Including full curing
8-hour Shift Output 2050 ~ 2400 pairs Theoretical value
16-hour Daily Output 4100 ~ 4800 pairs Theoretical value
Actual Capacity 80% ~ 90% of theoretical Affected by operator proficiency

Workshop, Power & Resource Requirements
Item Requirement & Parameter
Workshop Space 25m × 10m flat floor
Ambient Condition Temperature ≤40℃, no condensation
Power Supply 3×380V ±5%, 50Hz, total power ~85KW (Total Installed Power: About 90 KW)
Compressed Air Pressure: 0.7 ~ 0.8 MPa, dry & oil-free | Consumption: 0.6 ~ 0.8 m³/min
Cooling Water Circulation Clean water, temp ≤15℃, flow ≥6 m³/h
Operators 5 ~ 6 trained workers
Packaging & Transportation Overall Volume: Fit into 1 × 40HQ container | Total Weight: 10 ~ 15 tons
Export Package: Rainproof film + wooden pallet/iron frame | Delivery: Sea, air and combined delivery
After-Sales Service 1. Provide complete technical documents: operation manual, electrical drawings, workshop layout.
2. Overseas engineer on-site installation, commissioning and operator training.
3. 12 months warranty for non-artificial quality problems, free spare parts.
4. Lifetime technical guidance and spare parts supply after warranty.

Common Defects & Troubleshooting
Defect Root Cause Solution
Poor upper-sole adhesion Insufficient roughening / uneven release agent Strengthen surface treatment; standardize spraying
Internal bubbles Unqualified vacuum / raw material moisture Check air tightness; seal material tank
Material overflow Mold misalignment / excessive injection Adjust mold position; calibrate metering
Incomplete curing Low oven temp / short curing time Adjust heating parameters & line speed


Optional Upgrades & Turnkey Customization
Automatic Feeding and Multi-Formula
Automatic Feeding & Multi-Formula
Supports automatic feeding system to reduce manual labor, along with HMI multi-formula storage and one-click switching function.
MES and Unmanned Linkage
MES & Full Automation Linkage
Optional MES data management & traceability system, and fully automatic production linkage (unmanned auxiliary line).
Global Grid & Explosion-Proof
Global Grid & Explosion-Proof Config
Supports voltage & frequency customization for global markets, plus explosion-proof configuration for special workshops.

Frequently Asked Questions
01. Is the one-piece molding process different from traditional gluing?
Yes. This line adopts glue-free integral molding, which provides higher strength and longer service life.
02. Can molds be customized for different shoe sizes?
Yes, we customize molds and lasts according to your product drawings.
03. Can equipment adapt to different national power grids?
We support voltage and frequency customization for global markets.
04. What is the main daily maintenance work?
Clean mixing head and spraying robot daily; check temperature, pressure and air pressure per shift.
05. Can old production lines be partially upgraded?
We provide partial renovation solutions to save procurement cost.


Get Custom Sandal Production Line Solution

Free workshop layout design, technical consultation and equipment quotation available.

Official Website: www.haifengmachine.com
WhatsApp: +86 13566296633

RELATED PRODUCTS

RELATED NEWS

CONTACT US

To find out more about our products and solutions,please fill out the form below and one of our experts will get back to you shortly.

Please agree to the Privacy Policy before submitting.